You are planning to make modifications to an existing application. You have identified:

30% probability of delay of receipt of resources – cost $50,000.

20% probability that the resources will be $10,000 cheaper than planned.

25% probability that there will be a problem integrating with existing software, cost to fix $3,500.

30% probability that the development may be simpler than expected, savings $2,500.

5% probability of a design defect causing $5,000 of rework.

.Calculate the net expected value for the project risks and opportunities cited above.

.How much should you plan for your contingency reserve budget based on the above?

How much would you allocate for the management reserve?

What are your assumptions about these reserves?
ORDER THIS ESSAY HERE NOW AND GET A DISCOUNT !!!

 

You can place an order similar to this with us. You are assured of an authentic custom paper delivered within the given deadline besides our 24/7 customer support all through.

 

Latest completed orders:

# topic title discipline academic level pages delivered
6
Writer's choice
Business
University
2
1 hour 32 min
7
Wise Approach to
Philosophy
College
2
2 hours 19 min
8
1980's and 1990
History
College
3
2 hours 20 min
9
pick the best topic
Finance
School
2
2 hours 27 min
10
finance for leisure
Finance
University
12
2 hours 36 min
[order_calculator]